RYE 2014 ELECTION:  BACKGROUND ON WARRANT ARTICLES 7-11

Final Revision D -- Provided by the Rye Civic League

Quick links

Article 7

Article 8

Article 9

Article 10

Article 11

 

ARTICLE 7:  CONSERVATION BOND ($3,000,000)

 

Text of warrant article

 

To see if the Town will vote to raise and appropriate up to the sum of three million dollars ($3,000,000) to be placed in the Conservation Land Acquisition Fund for the acquisition of conservation easements or open space lands by the Town, all for the permanent protection of appropriate underdeveloped land in the Town of Rye, and to authorize the Conservation Commission and Selectmen to act on behalf of the town in connection with such acquisition of conservation easements or open space lands (subject to the hearing and procedural requirements of NH RSA Chapter 36-A) and to further authorize the issuance of not more than three million dollars ($3,000,000) of bonds and/or notes in accordance with the provisions of the Municipal Finance Act, NH RSA Chapter 33 as amended, and to authorize the Selectmen to issue and negotiate such bonds and/or notes and to determine the rates of interest thereon? (3/5 ballot vote required.)

This article is recommended by the Selectmen (3-0)

This article is recommended by the Budget Committee (8-0)

 

Background and explanation

 

            In 2003, the voters approved a $5 million bond issue for the purchase of conservation land and easements.  Those funds were exhausted in 2012 with the purchase of an easement on the Lium property on Washington Rd. for $725,000, however principal repayments and interest on the bonds will continue through 2020.

In 2013, the former Rand Lumber parcel on Wallis Rd. was sold.  The developer is seeking to develop the front portion and sell the back portion for conservation, at a reported price of $1.2 to $1.5 million.  Conservation Commission Chairman Jim Raynes has stated that there are a total of 3-4 parcels that may require the investment of conservation funds over the next few years.  If the bond passes, under New Hampshire law, the Conservation Commission would approve any land or easement purchases following a public hearing, and the approval of the Board of Selectmen would also be required.  Initially, Selectmen Musselman preferred that the voters individually approve each acquisition at the annual Town meeting, and Selectman Mills was undecided.  However, once a process was agreed to at the January 6, 2014 Board of Selectmen meeting, the Selectmen voted unanimously to recommend the warrant article.  An attempt to amend this warrant article at the Deliberative Session to require the Board of Selectmen to follow their own procedure, and to require an appraisal for each property, was defeated.

 

Links

 

Deliberative Session notes of the discussion regarding this warrant article:  Click here.

Video of the Deliberative Session discussion of this warrant article:  Click here.

Presentation by Tracy Degnan at the Deliberative Session:  Click here.

Town Minutes of the Deliberative Session:  Click here (pages 3-5).

Notes of January 6, 2014 Board of Selectmen meeting approving the process:  Click here.

Conservation Land Acquisition Approval Process agreed to at January 6, 2014 meeting:  Click here.

Video of the above:  Click here (entire meeting)

Town minutes of the January 6, 2014 Board of Selectmen meeting:  Click here (entire meeting).

Notes of discussion regarding Conservation Warrant Article at December 9, 2013 Selectmen’s meeting:  Click here.

Video of the above Click here (at 132:00 elapsed.  See in particular 156:44 where $1.5 million is mentioned)

Town minutes of the above:  Click here (pages 12-14).

Notes of discussion at December 12, 2013 Budget Committee meeting:  Click here.

Video of the above:  Click here (at 73:44 elapsed).

Town minutes of the above:  Click here (pages 3-5).

Notes of further discussion at December 23, 2013 BOS meeting:  Click here (no video available).

Town minutes of the above:  Click here (pages 1-4).

Video of the Budget Committee approving at Jan. 16, 2014 meeting:  Click here (5:51 elapsed)

 

ARTICLE 8:  TOWN HALL DESIGN ($250,000)

 

Text of warrant article

 

To see if the Town will vote to raise and appropriate the sum of two hundred fifty thousand dollars ($250,000) for the purpose of completing the design process, including Schematic Design, Design Development, the preparation of Construction Documents (including drawings and specifications) and the solicitation and analysis of competing construction bids from pre-qualified general contractors for the purposes of renovating the Town Hall 1839 building and building separate, connected new Town Hall office space. This project is under the direction of the Board of Selectmen with the advice and concurrence of the Town Hall Building Committee. This appropriation is in addition to the operating budget. (Majority vote required.)

This article is recommended by the Selectmen (3-0)

This article is recommended by the Budget Committee (9-0)

 

Background and explanation

           

            In 2011, the voters approved by a vote of 610-455, Warrant Article 14 for a structural analysis of Town Hall and a space needs study.  In late 2012, AG Architects, the firm hired to perform the work presented a sample design which showed a brick building connected to the existing white clapboard Town Hall.  The sample design purported to fulfill the Town’s space need of 15,090 sq. ft., including the existing Town Hall of 6,168 sq. ft.  Despite recommendations by the Selectmen and the Budget Committee, there was general opposition to the size and appearance of the building, and in 2012, the voters rejected Warrant Article 10 (by a vote of 484-830), which would have proceeded with the Design Development phase of the project.  Petitioned Warrant Article 27, which required a broader look at the options and an investigation of the square feet per employee of other towns passed 1070-268.

            During 2012, a Space Needs Committee was formed by the Selectmen.  It included a number of Town residents.  That Committee determined that a reduced space need of 10,500 sq. ft., plus or minus ten percent, would suffice.  In 2013, the voters approved Warrant Article 4 by a vote of 699-384 which provided $60,000 for the retention of an architect to produce schematic designs for two options:  An additional, separate building on the Town Hall site, and an extension to the existing building that would add a maximum of 1/3 to the existing length. 

            SMP Architecture was retained to provide the schematic designs and a Town Hall Committee was formed to oversee the process.  SMP suggested a design with a second building located approximately 20 feet from the existing one, but connected at ground level with a corridor buried underground below a plaza above.  The plaza would provide access to the second floor of both the new and old buildings from the adjoining parking lot of the Congregational Church, which is owned by the Town.  The first floor of both buildings would be accessible from the existing parking lot.  As required by 2013 Warrant Article 4, the Great Hall (Meeting Hall) on the second floor of the existing Town Hall, which is currently partitioned into individual offices, would be restored to its prior state for use by large assemblies.  The curvilinear staircases at the entry to the building would also be restored.  SMP determined, and the Town Hall Committee agreed, that the single building option was not feasible within the constraint permitted, given the space needs of the Town. 

            The current schematic design provides for 12,700 sq. ft., however the design and square footage are subject to further change as the project proceeds.  This schematic design has been scaled back somewhat since the November 7, 2013 presentation to the public, where concern was expressed with regard to the size.  The $250,000 requested in this Article will complete the design and allow bids to be obtained, such that the Town would be in a position to vote up or down a firm price for construction in March 2015. 

 

Links

 

Deliberative Session notes of the discussion regarding this warrant article:  Click here.

Video of the Deliberative Session discussion of this warrant article:  Click here.

Town Minutes of the Deliberative Session:  Click here (pages 5-6).

One page project summary and Concept Video played at Deliberative Session:  Click here.

Town Hall presentation video:  Click here.

Town Hall Facebook page:  Click here.

Document relating to the upstairs Meeting Room, or Great Hall:  Click here.

Video of Town Hall Committee Meeting, January 10, 2014:  Click here.

Town minutes of Town Hall Committee meeting, December 19, 2013:  Click here.

Notes of Town Hall Committee meeting, November 19, 2013:  Click here.

Video of above:  Click here.

Town minutes of above:  Click here.

Notes of Town Hall Committee Public Discussion, November 7, 2013:  Click here.

Town minutes of above:  Click here.

 

ARTICLE 9:  FRONT END LOADER ($175,000), FIRST YEAR COST:  $45,000

 

Text of warrant article

 

To see if the Town will vote to authorize the Selectmen to enter into a three year lease/purchase agreement for one hundred seventy-five thousand dollars ($175,000) for the purpose of leasing to purchase a front end loader for the Public Works Department and to raise and appropriate the sum of forty-five thousand dollars ($45,000) for the first year’s payment for that purpose. This lease agreement contains an escape clause.  This appropriation is in addition to the operating budget. (Majority vote required.)

This article is recommended by the Selectmen (3-0)

This article is recommended by the Budget Committee. (6-0)

 

Background and explanation

 

            At the Deliberative Session, Public Works Director Dennis McCarthy explained that this was not to replace the existing front end loader, but rather to replace a “bucket dozer” that had been purchased in 1986.  The latter is no longer needed due to a change in the way that they operate.  Normally, this type of equipment is purchased from funds accumulated in the Highway Equipment Capital Reserve Fund.  There have been warrant articles the past few years to add $100,000 each year to that Fund.  The voters approved both additions to the Capital Reserve, which increased taxes in the year made, as well as withdrawals from the Fund which do not affect taxes in the year made as the money has already been set aside.  The Capital Reserve earns only nominal interest, about .1 percent annually.

            While normally, equipment of this type is paid for out of the Capital Reserve, Warrant Articles 10 and 16 seek to withdraw $215,000 from the Capital Reserve, which has a current balance of approximately $278,000.  While Warrant Article 19 would add another $100,000 to the Capital Reserve, passage of that Warrant Article cannot be assured.  In any event, there would not be an extra $175,000 to pay for this equipment, thus it must be leased.  At the Deliberative Session, Mr. McCarthy estimated that the interest rate on the lease would be about 4 percent annually, amounting to approximately $12,000 over the life of the lease in extra charges relative to buying the equipment using cash.

            As discussed at the Deliberative Session, the intent is that future years lease payments will be added to the operating budget, and would not be separate warrant articles.  While the lease would enable the Town to return the equipment and get out of the lease, that is not the intent, and if the Town wants to retain the equipment, taxes would be raised for an additional 2-3 years until the lease has ended, at which point some expenditure may be required to purchase the equipment from the lessor.

 

Links

 

Deliberative Session notes of the discussion regarding this warrant article:  Click here.

Video of the Deliberative Session discussion of this warrant article:  Click here.

Town Minutes of the Deliberative Session:  Click here (pages 6-7).

Town 2014-2019 Capital Improvement Plan (“CIP”):  Click here.

Notes of the December 9, 2013 Board of Selectmen meeting where this was approved:  Click here.

Video of the above meeting:  Click here (171:23 elapsed).

Town minutes of above:  Click here (pages 14 and 15)

Notes of the December 12, 2013 Budget Committee meeting where this was recommended:  Click here.

Video of the above meeting:  Click here (100:38 elapsed)

Town minutes of the above:  Click here (page 5)

 

ARTICLE 10:  SIX-WHEEL DUMP TRUCK ($150,000)

 

Text of warrant article

 

To see if the Town will vote to raise and appropriate the sum of one hundred fifty thousand dollars ($150,000) to purchase a new six wheel dump truck to replace an existing older, high mileage six wheel dump truck and to authorize the withdrawal of one hundred fifty thousand dollars ($150,000) from the Highway Equipment Capital Reserve Fund created in 1994 for this purpose. This appropriation is in addition to the operating budget. (Majority vote required.)

This article is recommended by the Selectmen (3-0)

This article is recommended by the Budget Committee. (6-0)

 

Background and explanation

 

            The six wheel dump trucks are used for plowing and other uses related to Public Works.  In 2013, a decision was made to defer replacement.  Now, there are two trucks that need replacing.  When the time comes to replace the trucks later in 2014, a decision will be made as to which one will be replaced.  The trucks have only 60,000 to 70,000 miles on them, but are 16-17 years old, Public Works Director Dennis McCarthy said (however, the CIP Plan states that the mileages are 31,662 and 25,500, respectively).  The key determinant of life is the number of winters they have gone through, according to Mr. McCarthy.

            There is $278,200 in the Highway Equipment Capital Reserve Fund, which will be drawn down to replace this truck and another one (see Article 16), for a total of $215,000.  The $175,000 front end loader being replaced this year (see Article 9) will need to be leased, at a $12,000 cost over the term of the lease for interest, as there is not enough in the Capital Reserve to pay for all three pieces of equipment.  The Capital Reserve has been added to at a rate of $100,000 annually in recent years.  Such additions increase the tax rate in the year that the Capital Reserve is added to, but there is no direct tax effect when the money is withdrawn.  However, withdrawals reduce the Capital Reserve balance, which will need to be replenished if it is to be used for equipment purchases in the future.

 

Links

 

Deliberative Session notes of the discussion regarding this warrant article:  Click here.

Video of the Deliberative Session discussion of this warrant article:  Click here.

Town Minutes of the Deliberative Session:  Click here (page 7).

Town 2014-2019 Capital Improvement Plan (“CIP”):  Click here (see pages 35 and 38).

Notes of the December 9, 2013 Board of Selectmen meeting where this was approved:  Click here.

Video of the above meeting:  Click here (173:10 elapsed).

Town minutes of above:  Click here (page 15)

Notes of the December 12, 2013 Budget Committee meeting where this was recommended:  Click here.

Video of the above meeting:  Click here (106:39 elapsed)

Town minutes of the above:  Click here (page 6)

 

 

ARTICLE 11:  WALLIS RD. BOX CULVERT REPLACMENT ($150,000)

 

Text of warrant article

 

To see if the Town will vote to raise and appropriate the sum of one hundred fifty thousand dollars ($150,000) for the purpose of replacing the Wallis Road Box Culvert by public bid. Said sum to include engineering services for bidding and inspecting of the project. This appropriation is in addition to the operating budget. (Majority vote required.)

This article is recommended by the Selectmen (3-0)

This article is recommended by the Budget Committee. (9-0)

 

Background and explanation

 

            This culvert is the easternmost of two behind the Red Roof Market at the intersection of Wallis Rd. and Ocean Boulevard.  The surrounding area is the subject of ongoing litigation between the Town and the Beliveaus, property owners at 21 Wallis Rd., the northeast corner of Wallis Rd. and Appledore Ave.  According to admissions by the Town of Rye in court filings, in September 1997, the Town began a multi-year salt marsh restoration project which involved the installation of new twin box culverts approximately 164 feet to the west of the existing culvert and the main channel of Parsons Creek was relocated to align with the new culverts.  According to the Beliveau’s court filing, this caused Parsons Creek to flow through their land, reducing the available uplands upon which they could build.

            In 2011, the Believeau’s were denied a variance by the Rye Zoning Board of Adjustment to tear down three existing structures and build a 3630 sq. ft. house.  While the Rockingham Superior Court affirmed, the New Hampshire Supreme Court, on August 30, 2013 reversed, sending the case back to the Superior Court for further fact finding.  Meanwhile, on August 2, 2013, the Beliveaus had filed a second case, seeking compensation for the diminution in value of their property and requesting that the court “[o]rder Defendant [i.e. the Town of Rye] to restore Parsons Creek and [their] Property to its original conditions.”  Both cases remain pending.

            According to information provided by Public Works Director Dennis McCarthy at the Deliberative Session, the Town had wanted to fill in the culvert, under which is the original watercourse flowed, however, the State, the EPA and the Army Corps of Engineers would not permit this, although they would permit the culvert to be replaced with one of the same size as the existing one.  Mr. McCarthy stated that the culvert is badly deteriorated and is in need of replacement.

            In response to a question from the audience, the Selectmen and Town Counsel denied that the ongoing litigation would have any impact on the replacement of the culvert, but did not explain why.  At the February 19, 2014 Candidates Night, Selectman Mills acknowledged that a mediation hearing earlier that day had been to “no avail.”

 

Links

 

New Hampshire Supreme Court decision in the Beliveau’s zoning appeal:  Click here

United States District Court filings in the second Beliveau case seeking restoration of the creek:  Click here

Answer of Town of Rye in the above case:  Click here

Video of Selectman Mills stating that the mediation was to “no avail”:  Click here (4:05 elapsed)

Deliberative Session notes of the discussion regarding this warrant article:  Click here.

Video of the Deliberative Session discussion of this warrant article:  Click here.

Town Minutes of the Deliberative Session:  Click here (page 8).

Town 2014-2019 Capital Improvement Plan (“CIP”):  Click here (see page 37).

Video of the January 13, 2014 Board of Selectmen meeting approving the culvert:  Click here (106:00 elapsed).

Town minutes of above:  Click here (page 7)

Video of the January 16, 2014 Budget Committee meeting recommending it:  Click here (30:21 elapsed)