1. Â Non-public sessions were conducted after this meeting and the prior one. Â Discussion was apparently regarding acquisition of a new site for Town Hall. Â A Special Town Meeting may be needed to approve that.
2. Â Reasons for failure of $4.1 million Town Hall warrant article in 2015 were discussed. Â Opposition e-mail from a builder in Rye, and a letter to the editor opposing the project from the former Chairman of the Town Hall Committee were discussed.
3. Â Work session was conducted with representatives of the UNH Survey Center regarding an upcoming survey of Rye residents on Town Hall issue. Â Questions discussed included:
a. Â The importance to Town residents of preserving historical features of the existing building.
b. Â The possibility of demolishing the existing Town Hall.
c. Â The feasibility of continuing to use the Rye Schools for elections while school is in session.
7/21/15
1. Â Recent e-mails between Town Hall Committee members have violated the right-to-know law. Â In the future, discussions between Town Hall Committee members will need to occur during public meetings.
2. Â Further work session was conducted with UNH Survey Center on resident questionnaire on Town Hall.
3. Â Survey results are expected by mid- to late-September.
7/28/15
1. Â The survey was essentially finalized. Â A final draft will be circulated by e-mail, with responses only to Town Finance Director Cyndi Gillespie to maintain compliance with the right-to-know law. Â The final version will be sent to the UNH Survey Center by the Town Hall Committee Chairman by the end of the week.
2. Â There was extensive discussion regarding how to present the tax impact and ascertain residents’ willingness to accept various levels of taxation to pay for Town Hall.
3. Â It was revealed that Hutter, the low bidder for the Town Hall project in early 2015, estimated that $950,000 of it’s approximately $3.3 million bid was related to renovation of the existing building, with the remainder relating to the new building. Â The warrant article amount of $4.1 million exceeded the bid amount due to contingencies and costs to be borne by the Town directly, rather than the contractor.
4. Â The $4.1 million warrant article in 2015 did not include $350,000 in expenditures (primarily with architects) previously approved by voters. Â The total project cost thus would have been $4.45 million. Â Any revised project is likely to require the expenditure of additional architectural costs.